Pergola Builder
Shopping list
Everything ground-contact pressure-treated. The posts and beams are the long-lead items; many yards order 6×6s and long 2×10s in, so call ahead.
| Item | Qty | Each | Total |
|---|---|---|---|
| 6×6×12 pressure-treated, ground contact (posts) | 4 | $64.98 | $259.92 |
| 6×6×8 pressure-treated (knee braces) | 2 | $43.32 | $86.64 |
| 2×10×16 pressure-treated (beams) | 4 | $40.34 | $161.35 |
| 2×6×12 pressure-treated (rafters) | 12 | $16.35 | $196.24 |
| 2×2×8 pressure-treated (purlins) | 27 | $3.98 | $107.46 |
| Fast-setting concrete, 50 lb (10 per hole) | 40 | $6.48 | $259.20 |
| All-purpose gravel, 0.5 cu ft (6″ under each post, 2 per hole) | 8 | $5.48 | $43.84 |
| ½″ × 10″ galvanized carriage bolt, nut & 2 washers (beams, brace tops) | 12 | $5.48 | $65.76 |
| ⅜″ × 6″ structural screws, 12-pack (brace feet) | 1 | $16.98 | $16.98 |
| Galvanized hurricane tie (H2.5A) | 24 | $1.18 | $28.32 |
| Connector screws #9 × 1½″, 1-lb box (hurricane ties) | 1 | $14.98 | $14.98 |
| 3″ exterior deck screws, 5-lb box (rafters, purlins · about 192) | 1 | $39.98 | $39.98 |
| Exterior stain / sealer, 1 gal (after the PT dries) | 1 | $42.98 | $42.98 |
| Total | $1,323.65 |
Tools: post-hole digger or rented auger, digging bar, string line and stakes, 4′ level, post level, circular saw, jigsaw (rafter tails), drill/driver, ½″ × 12″ bit, socket set, two tall ladders, clamps, wheelbarrow. Two or three helpers for the beams.
Every cut laid onto standard boards, longest first, with a ⅛″ saw kerf between pieces. Hatched space at the end of a board is offcut, and ×3 means cut three boards the same way. Use this at the saw to cut one board at a time.
2×10 × 16′
4 boards94% yield2×6 × 12′
12 boards99% yield2×2 × 8′
27 boards83% yieldPosts are buried 36″ in concrete with gravel under them, beams sandwich the posts with through-bolts, and 45° knee braces stop the frame racking along the beams (across the width, the posts' 36″ concrete footings do that job). Beam tops sit at 8′ 8″: a 12′ post minus 36″ in the ground and 4″ to cut level in place, for about 8′ of clear headroom under 2×8 beams (7′ 10¾″ under 2×10s). Check your frost depth and setbacks, and call 811 before you dig.
- 1
Shopping list
Everything ground-contact pressure-treated. The posts and beams are the long-lead items; many yards order 6×6s and long 2×10s in, so call ahead.
Above 10′ × 10′ this always uses 6×6 posts: 4×4s this tall on a footprint this big sway and twist.Item Qty Each Total 6×6×12 pressure-treated, ground contact (posts) 4 $64.98 $259.92 6×6×8 pressure-treated (knee braces) 2 $43.32 $86.64 2×10×16 pressure-treated (beams) 4 $40.34 $161.35 2×6×12 pressure-treated (rafters) 12 $16.35 $196.24 2×2×8 pressure-treated (purlins) 27 $3.98 $107.46 Fast-setting concrete, 50 lb (10 per hole) 40 $6.48 $259.20 All-purpose gravel, 0.5 cu ft (6″ under each post, 2 per hole) 8 $5.48 $43.84 ½″ × 10″ galvanized carriage bolt, nut & 2 washers (beams, brace tops) 12 $5.48 $65.76 ⅜″ × 6″ structural screws, 12-pack (brace feet) 1 $16.98 $16.98 Galvanized hurricane tie (H2.5A) 24 $1.18 $28.32 Connector screws #9 × 1½″, 1-lb box (hurricane ties) 1 $14.98 $14.98 3″ exterior deck screws, 5-lb box (rafters, purlins · about 192) 1 $39.98 $39.98 Exterior stain / sealer, 1 gal (after the PT dries) 1 $42.98 $42.98 Total $1,323.65 Tools: post-hole digger or rented auger, digging bar, string line and stakes, 4′ level, post level, circular saw, jigsaw (rafter tails), drill/driver, ½″ × 12″ bit, socket set, two tall ladders, clamps, wheelbarrow. Two or three helpers for the beams.
- 2
Cut list
Posts go in as full 12′ lengths and get cut level in place (Step 4) to about 11′ 8″ (8′ 8″ above grade), so don't pre-cut them. Rafter tails get a shaped cut on both ends: trace one, cut it with a jigsaw, use it as the pattern.
Tag Part Length Qty Cut P Post (6×6) 144″ 4 full 12′; cut level in place at 8′ 8″ above grade K Knee brace (6×6) 39¾″ 4 45° plumb + 45° level (long point) B Beam board 180″ 4 decorative tail both ends R Rafter 143″ 12 decorative tail both ends U1 Purlin 82″ 12 square; joints centered on a rafter U2 Purlin 80¼″ 12 square; joints centered on a rafter U3 Purlin 17¾″ 12 square; joints centered on a rafter Seal every cut end of pressure-treated lumber with end-cut preservative. Factory treatment doesn't reach the core. - 3
Lay out and set the posts
Call 811 first. Stake the four corners at 10′ × 12′ outside to outside, run string lines, and square them: the diagonals must match within ¼″.
- Dig 16″ holes 42″ deep. Tamp 6″ of gravel in the bottom.
- Stand each post on the gravel, plumb it on two faces with a post level, and brace it with two stakes and scrap 2×4s.
- Pour 10 bags of fast-set per hole, water per the bag, and crown the top so water runs away from the post.
Keep the posts on the string line and plumb before the concrete sets: 15 minutes with fast-set. Leave the braces on overnight. - 4
Cut the posts and hang the beams
Mark the post standing on the highest ground at 8′ 8″ above grade, then transfer that height to every post with a laser or a water level. Cut them all level in place (a circular saw from two sides, finish with a handsaw).
- Clamp a 2×10 to each face of each post row, tops flush with the post tops, overhanging 18″ past the end posts.
- Drill ½″ through beam, post, beam and drive two carriage bolts per post, staggered.
Beam boards are heavy up there. Set them on temporary 2×4 cleats screwed to the posts, then clamp and drill. - 5
Knee braces
4 braces at 45°, each slipped up between the two beam boards from the inside of a post. The plumb end sits tight on the post, the level-cut top end is buried in the beam.
Mark each post 21⅞″ below the underside of the beam: that's where the brace's bottom point lands. The top then reaches 28⅛″ along the beam from the post, with its level cut 3″ below the beam top.
One carriage bolt through beam, brace, beam at the top, centered in the overlap; two ⅜″ × 6″ structural screws through the brace foot into the post, pre-drilled.
Check: posts still plumb both ways before the braces lock them. They hold whatever shape you give them. - 6
Rafters
12 rafters on edge across both beams, 16″ on center, overhanging 10″ past each beam, tails both ends.
- Mark the layout on the beam tops with a story stick so both beams match.
- Toe-screw each rafter into each beam pair with two 3″ screws, then fasten a hurricane tie (H2.5A) on the outer face of each beam with #9 × 1½″ connector screws, every hole filled.
Sight down the rafter row before fastening and flip any with a crown down; crowns go up. - 7
Purlins
12 rows of 2×2 purlins across the rafter tops, 12″ apart. One 3″ screw at every crossing, pre-drilled near the ends.
Land each joint on a rafter and stagger joints from row to row. Purlins double the shade and stiffen the rafters against twisting.
- 8
Done
10′ × 12′ pergola with 7′ 10¾″ of clear headroom. Re-tighten every bolt after a month as the PT dries.
Let the wood dry (water soaks in instead of beading, usually 2–3 months), then stain or seal it.
Want more shade? Run shade cloth or a retractable canopy on the purlins, or train a vine up the posts.
Cut diagram
Every cut laid onto standard boards, longest first, with a ⅛″ saw kerf between pieces. Hatched space at the end of a board is offcut, and ×3 means cut three boards the same way. Use this at the saw to cut one board at a time.
2×10 × 16′
4 boards94% yield2×6 × 12′
12 boards99% yield2×2 × 8′
27 boards83% yieldPosts are buried 36″ in concrete with gravel under them, beams sandwich the posts with through-bolts, and 45° knee braces stop the frame racking along the beams (across the width, the posts' 36″ concrete footings do that job). Beam tops sit at 8′ 8″: a 12′ post minus 36″ in the ground and 4″ to cut level in place, for about 8′ of clear headroom under 2×8 beams (7′ 10¾″ under 2×10s). Check your frost depth and setbacks, and call 811 before you dig.